NEW ADDAX FACILITIES

Project Description

The project is located at the Federal Lighter Terminal, Calavi Port Complex, along the Road C behind the FLT #4 jetty, in front of FLT water treatment and power Plant. ADDAX desires to have the Main operational base in Benin, with comprehensive facilities as per below project’s details.

The facilities include:

  1. Stacking Area: the total area is 51,230 m² with concrete slab of 250mm thick, reinforced with two layers of BRC, composed by 40,000 m² free industrial area and 11,230 m² of quay apron
  2. Warehouse & Office: a warehouse of 4,000 m² with 800 m² of overhang roofing and attached double floor offices 2×200 m². The foundations of the building is composed by No. 114 Auger piles Dia= 600mm and 16m depth and No. 46 Pile caps where the steel structure would be erected. The warehouse would accommodate a ~30 m² cold room
  3. Pipe inspection shed of 1,210 m²: the foundation of the building is composed by No. 42 Auger piles Dia= 600mm and 16m depth and No.12 Pile caps where the steel structure would be erected
  4. Fencing & Gate Work: the fencing work – total length of 792 m – includes 132m concrete fence and 660m welded wire mesh panel fence with concertina wire. Three (3) no. double leaf steel gates of width 10m, and 3 no pedestrian gates are designed to provide access to the facilities
  5. Drainage system
  6. Covered Car Park for no.16 cars
  7. MEP works for the facilities, including water and power supply

Project Details

Completion Date
May 2013 – Aug 2014
Client
Addax Facilities
Info
Main Contractor:
WACCEC (PIL)