NLNG ACCESS ROAD AT HELICONIA PARK

Project Description

The scope of work is to construct the access road from the roundabout to NLNG new office and to reconnect with an existing road across Heliconia Park on the other side of the office. The road is 300 m long and 16.80 m wide (width of median strip is 0.80 m) and is one layer of compacted sand, one layer of sand and cement stabilisation (260 mm compacted thickness) and 100 mm asphalt in two layers (60 mm binder + 40 mm wearing courses). It is bordered by hard kerbs with footways and has 1 culvert and landscaped with drainage system. Street lighting is provided by 16 double bracket lighting poles along median strip plus 4 single bracket lighting poles located at future NLNG’s Head Office access. Road is completed with road marking and traffic signs.

Project Details

Client
NLNG S.A
Info
Main Contractor
WACCEC (PIL)
Period
Apr 2011 –Sep 2012