NLNG ROUNDABOUT AT HELICONIA PARK

Project Description

The scope of work is to create a roundabout on a dual carriage way near the Eastern by-pass for access to NLNG’s new office, planned at Heliconia Park. The existing dual carriageway is 15.80 metres wide and the third road which is 16.80 (width of median strip is 0.80 metres) metres wide will be added at right angles. The inner circle of the roundabout has a diameter of 40.00 metres and the road width at the circumference is 11.00 metres. The road specification is one layer of compacted sand, one layer of sand and cement stabilisation (260mm compacted thickness) and 100 mm asphalt in two layers (60mm binder + 40mm wearing courses). The roundabout is bordered by hard kerbs with footways on the outer circle. It is completed with 2 culverts and landscaped with a drainage system. Street lighting is provided by 8 outer lighting poles and roundabout is completed with road marking and traffic signs.

Project Details

Client
NLNG S.A
Info
Main Contractor
WACCEC (PIL)
Period
Jan 2011 - May 2011